Tuesday, 12 December 2017

WEEK 16 (FYP 2)

Activity:
  • Adjust and finalize the fyp thesis .
Objective:
  • Complete the fyp thesis.
  • Make sure that all the information of this project was included in the thesis.
  • Make sure that there are no mistake and all the information was correct and also was arranged nicely.
  • Make sure that the Plagiarism Result below 20%.

Result :

         
Figure 1: Softcopy FYP Thesis front page.



Figure 2: Plagiarism Result




Conclusion:
  • I have successfully complete the fyp thesis.

Tuesday, 5 December 2017

WEEK 15 (FYP 2)

Activity:

FYP 2 INDUSTRY DAY OF STUDENT SEMESTER JULY 2017


                                 o   Date      : 15th November 2017(Wednesday)
                                 o   Time      : 9.00am – 12.00pm
                                 o   Venue    : UNIKL BMI Gemilang Hall


Figure 1 : Prove Picture

WEEK 14 (FYP 2)

Activity:
  • Do the poster for Industry Day presentation .
Objective:
  • Design a poster about this project.
  • Make sure that all the information of this project was display included and correct.
  • Include just needed information and make sure that the information is not so pack.

Result :

           

Figure 1: Poster.




Conclusion:
  • I have successfully designed a poster that gives full information about this project.

WEEK 13 (FYP 2)

FYP 2 BRIEFING OF STUDENT SEMESTER JULY 2017

Attend for first briefing Final Year Project 2 for degree student.


                            o   Date      : 3th November 2017(Wednesday)
                            o   Time      : 3.00pm – 5.00pm
                            o   Venue    : TTL1

·         
The attendances is compulsory 

In the briefing, the FYP committees have briefed us about:

         Final Briefing, 
     

WEEK 12 (FYP 2)

Activity:
  • Start the assemble the Stepper Motor circuit on the strip board .
Objective:
  • Construct the circuit on the strip board.
  • Make sure all the connection was correct.
  • Make sure that the Stepper Motor can run and operate same as when simulation was conducted.

Result :

           


Figure 1: Stepper Motor circuit construction.






                                          Figure 2 : Circuit soldering.






Conclusion:
  • I have successfully construct and solder the circuit on strip board and run also operate the Stepper Motor  same as when it was simulated on breadboard.

WEEK 11 (FYP 2)

FYP 2 BRIEFING OF STUDENT SEMESTER JULY 2017

Attend for first briefing Final Year Project 2 for degree student.


                                                 o   Date      : 20th October 2017(Friday)
                                                 o   Time      : 3.00pm – 5.00pm
                                                 o   Venue    : TTL1

·         
The attendances is compulsory 

In the briefing, the FYP committees have briefed us about:

         Abstract Writing, 
     Poster,

WEEK 10 (FYP 2)

Activity:
  • Start the assemble the LCD circuit on the strip board .
Objective:
  • Construct the circuit on the strip board.
  • Make sure all the connection was correct.
  • Make sure that the LCD can display word same as when simulation was conducted.

Result :

             

Figure 1: LCD circuit construction.



Figure 2 : LCD circuit construction.



Figure 3 : LCD Display.

Conclusion:
  • I have successfully construct and solder the circuit on strip board and display the LCD same as when it was simulated on breadboard.